Edwardsport, IN
47528
United States of America
Latitude: 38.8057136535645
Longitude: -87.2480850219727
Active as of 1/2010
This plant would only run 30% of the time. Costs have risen 18% from the earlier projection, with ratepayers likely to be forced to pay the bill. The plant is receiving 460 millionin government incentives. (Jan 2009)
Cinergy was aquired by Duke Energy in 2005. Vectran was early partner, but withdrew in mid 2007. Rail spur also proposed.
Proposed to come online in 2012.