Causey Rd
Telogia, FL
32360
United States of America
Latitude: 30.334718
Longitude: -84.817841
Approved for $2,962,718 Incentive Tax Credit under Section 1603 of the American Reinvestment and Recovery Act.
2/2009 bought by Multitrade
9/2008 bought by GreenHunter Energy
2009: "In 1986 […] General Electric started up a 14 MW facility about 30 miles southwest of Tallahassee. It’s still here and in operation" … "Timber Energy Resources, as it was called, was sold in 1998 to KTI, Inc., which upgraded the operation and ran it successfully, before selling it. This began a series of ownerships, including Green Hunter Energy, which in February of [2009] sold it to Multitrade Biomass Holdings."
"In January 2008 the Telogia plant sustained a catastrophic boiler failure, when a low water condition caused a meltdown of the boiler internals. In 23 degree F temperature, water accumulation had frozen up in the instrument air lines going to the boiler’s feedwater pump, causing it to cavitate, and the boiler to subsequently run out of water."
Base biomass fuels include bark, green chips, sander dust, sawdust, hogged fuel from land clearing acitivities, yard waste and peanut hulls. Alternate fuels comprise mixed non-recyclable fibers, suitable manufacutring residues, confidential documents and off-specification commodity wastes.